Resources/ Guides · 9 min read

OEE & TEEP: The Complete Guide for Plant Leaders

OEE (Overall Equipment Effectiveness) measures how much of your planned production time is genuinely productive — Availability × Performance × Quality. TEEP extends that to all calendar time. This guide covers both: the formulas, a worked example, what “good” looks like, the losses they expose, and how to turn the number into a dollar your finance team will sign.

Updated June 20, 2026

What is OEE?

Overall Equipment Effectiveness (OEE) is the single most widely used measure of manufacturing productivity. It answers one question: of the time you planned to produce good parts, how much did you actually spend producing good parts at full speed? A score of 100% means you made only good parts, as fast as the equipment can run, with no stop time — perfect production.

OEE is the product of three factors, each scored from 0–100%:

OEE = Availability × Performance × QualityMultiplicative — a weak factor caps the whole score.
  • Availability — the share of planned production time the line was actually running (lost to breakdowns, changeovers, and unplanned stops).
  • Performance — how close the line ran to its ideal cycle time while running (lost to minor stops and reduced speed).
  • Quality — the share of produced parts that were good first time (lost to scrap, rework, and startup rejects).

Because the factors multiply, OEE is unforgiving: a line that is 90% available, runs at 90% of rate, and yields 90% good parts scores just 73% (0.9 × 0.9 × 0.9), not 90%. That is the point — OEE surfaces compounding losses a single metric would hide.

What is TEEP — and how is it different?

OEE measures effectiveness against the time you scheduled. Total Effective Equipment Performance (TEEP) measures it against all the time there is — every hour on the calendar. It adds a fourth factor, Utilization:

TEEP = OEE × UtilizationUtilization = Planned Production Time ÷ All Calendar Time

Where OEE asks “how well did we run when we were scheduled to run?”, TEEP asks “how much of our total capacity are we actually using?” A plant running a single 8-hour shift can have excellent OEE and poor TEEP — the equipment sits idle two-thirds of the day. TEEP is the metric for capacity and capital-expansion decisions; OEE is the metric for shop-floor improvement.

How to calculate OEE (worked example)

Take a shift with 480 planned minutes. The line is down 47 minutes (breakdown + changeover), so it runs 433 minutes. It produces 14,400 parts at an ideal rate of 40 parts/minute, and 220 of those parts are defective.

FactorCalculationResult
Availability433 run ÷ 480 planned90.2%
Performance14,400 parts ÷ (433 min × 40/min)83.1%
Quality(14,400 − 220) ÷ 14,40098.5%
OEE0.902 × 0.831 × 0.98573.8%
OEE worked example — one 480-minute shift

The three factors also tell you where to look: availability and performance are dragging this line, not quality. That diagnosis — not the headline number — is where the money is.

What is a good OEE score?

The figures below are the benchmarks most commonly cited across discrete manufacturing. Treat them as orientation, not gospel — “good” depends heavily on process, product mix, and how honestly you define planned time.

ScoreInterpretation
~85%World-class for discrete manufacturers (≈ 90% availability × 95% performance × 99.9% quality).
~60%Typical for manufacturers not yet measuring OEE systematically — substantial room to improve.
~40% or belowCommon for plants just starting out; usually low-hanging fruit, not a crisis.
Commonly cited OEE benchmarks (discrete manufacturing)
Watch the denominator The fastest way to fake a good OEE score is to shrink “planned production time” — excluding stoppages as “not scheduled.” A number you can trust starts from an honest definition of planned time and is reconciled the same way every shift.

The Six Big Losses

OEE is most useful when you decompose it into the Six Big Losses — the standard taxonomy that maps every lost minute or part to one of the three factors. Fix the loss, and the factor (and OEE) moves.

LossOEE factorExample
BreakdownsAvailabilityUnplanned equipment failure or stoppage
Setup & adjustmentsAvailabilityChangeovers, material changes, warm-up
Idling & minor stopsPerformanceJams, misfeeds, sensor faults, blocked flow
Reduced speedPerformanceRunning below ideal cycle time, wear, derating
Process defectsQualityScrap and rework during stable production
Startup rejectsQualityDefects during warm-up or after a changeover
The Six Big Losses, mapped to the OEE factors

From measurement to verified savings

Measuring OEE is the easy part. The hard part — and the part that pays — is turning each loss into a ranked, owned action and then proving the savings actually landed. Most programs stall here: opportunities are guessed, savings are estimated on a slide, and the number never reconciles with the P&L.

That gap is exactly what KaizenFlow is built to close. It connects to the systems already producing your OEE data (MES, SCADA, ERP, historians), uses an AI ensemble to rank every loss by dollar impact and confidence, and then reconciles the result against a normalized baseline — so a recommendation becomes a verified, finance-signed figure rather than a projection.

The shortcut OEE tells you where the loss is. A closed loop — connect, surface, decide, verify — tells you what it was worth. See how the platform turns OEE losses into a verified savings ledger, or book a walkthrough against your own line.

Frequently asked

What is the difference between OEE and TEEP?

OEE measures effectiveness against planned production time; TEEP measures it against all calendar time by adding a Utilization factor (TEEP = OEE × Utilization). OEE is for shop-floor improvement; TEEP is for capacity and capex decisions.

Is 100% OEE possible?

In theory, 100% means only good parts, made as fast as possible, with no stop time. In practice it is a ceiling to measure against, not a target — world-class for discrete manufacturing is commonly cited around 85%.

What data do I need to calculate OEE?

Three things per piece of equipment: run time vs planned time (availability), actual output vs ideal cycle time (performance), and good parts vs total parts (quality). Most of this already exists in your MES, SCADA, or historian.

How is OEE turned into savings?

By decomposing it into the Six Big Losses, ranking each loss by dollar impact, assigning an owner and action, and then measuring the before/after against a normalized baseline so the savings can be verified — not just estimated.

© 2026 KaizenFlow AI

ResourcesPlatformSecurityContact